PMP?當(dāng)天每日一練試題地址:www.njjt123.com/exam/ExamDay.aspx?t1=33
往期PMP?每日一練試題匯總:www.njjt123.com/class/27/e33_1.html
PMP?每日一練試題(2022/6/23)在線測(cè)試:www.njjt123.com/exam/ExamDay.aspx?t1=33&day=2022/6/23
點(diǎn)擊查看:更多PMP?習(xí)題與指導(dǎo)
PMP?每日一練試題內(nèi)容(2022/6/23)
試題1
一個(gè)用于替換過(guò)時(shí)交易處理系統(tǒng)的解決方案的商業(yè)論證已獲得批準(zhǔn)。然而,預(yù)算僅限于在線交易,這項(xiàng)信息應(yīng)記錄在哪一項(xiàng)文件中?查看答案
試題參考答案:B
試題2
當(dāng)你準(zhǔn)備風(fēng)險(xiǎn)應(yīng)對(duì)的時(shí)候,你識(shí)別到了額外的風(fēng)險(xiǎn)。你應(yīng)該怎么辦?查看答案
試題參考答案:B
試題3
During the approval meeting with the stakeholders,another stakeholder.who has not previously provided input,challenge s the project baseline.After lengthy discussions, it becomes clear that final approval cannot be given.What is the appropriate action for the project manager to take?()查看答案
試題參考答案:A
試題4
一個(gè)國(guó)際項(xiàng)目團(tuán)隊(duì)分布在四個(gè)國(guó)家。其中一個(gè)外包團(tuán)隊(duì)簽訂的是固定總價(jià)合同,該團(tuán)隊(duì)預(yù)計(jì)項(xiàng)目進(jìn)度難以按計(jì)劃完成,估算延遲12個(gè)星期。項(xiàng)目經(jīng)理應(yīng)該怎么做?查看答案
試題參考答案:B
試題5
在與相關(guān)方一起召開(kāi)的項(xiàng)目計(jì)劃介紹會(huì)上,相關(guān)各方討論了某個(gè)問(wèn)題并形成解決方案。會(huì)后某一天,項(xiàng)目經(jīng)理收到一封來(lái)自關(guān)鍵相關(guān)方的電子郵件,說(shuō)他們對(duì)解決方案改變了主意。項(xiàng)目經(jīng)理首先應(yīng)該嘗試下列哪項(xiàng)沖突解決技巧?查看答案
試題參考答案:B
試題6
A project manager is notified that a software developer for a critical section of code will be out of the office for three wee ks. This task is not part of the critical path. What should the project manager do next?查看答案
試題參考答案:B
試題7
該項(xiàng)目的完工估算是多少?它說(shuō)明什么?()查看答案
試題參考答案:A
試題8
已經(jīng)決定使用瀑布管理項(xiàng)目。然而,由于需求不明確,軟件將在短時(shí)間內(nèi)使用Scrum進(jìn)行開(kāi)發(fā)。在從組織內(nèi)部獲得團(tuán)隊(duì)之后,項(xiàng)目經(jīng)理意識(shí)到組織在幾個(gè)關(guān)鍵領(lǐng)域缺乏技術(shù)專長(zhǎng),將需要從供應(yīng)商獲得外部資源。然而,本組織希望保留其對(duì)所進(jìn)行工作的戰(zhàn)略酌處權(quán)。對(duì)于項(xiàng)目經(jīng)理來(lái)說(shuō),為了最大限度地與供應(yīng)商協(xié)作,最好的承包技術(shù)是什么?查看答案
試題參考答案:A
試題9
項(xiàng)目所在國(guó)家的政治局勢(shì)不穩(wěn)定,需要與當(dāng)局官員建立良好關(guān)系才能保證物資供應(yīng)。該國(guó)目前在進(jìn)行總統(tǒng)換屆選舉,兩名候選人分別找到了你。其中一名候選人向項(xiàng)目尋求1萬(wàn)美元政治獻(xiàn)金,另一名要求幫助搭建選舉用的演講臺(tái)。你應(yīng)該如何行動(dòng)?()查看答案
試題參考答案:D
試題10
A company has a collection of projects,A, B and C. These projects are prioritized across a common set of criteria based o n the company's objectives. Project B has high priority because it will increase the company's market share and reduce dependency on unreliable suppliers. What activity is being per formed?查看答案
試題參考答案:B
信管網(wǎng)訂閱號(hào)
信管網(wǎng)視頻號(hào)
信管網(wǎng)抖音號(hào)
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請(qǐng)以權(quán)威部門公布的內(nèi)容為準(zhǔn)!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛(ài)好者、大學(xué)生提供專業(yè)、高質(zhì)量的課程和服務(wù),解決其考試證書(shū)、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過(guò)深研歷年考試出題規(guī)律與考試大綱,深挖核心知識(shí)與高頻考點(diǎn),為學(xué)員考試保駕護(hù)航。面授、直播&錄播,多種班型靈活學(xué)習(xí),滿足不同學(xué)員考證需求,降低課程學(xué)習(xí)難度,使學(xué)習(xí)效果事半功倍。
發(fā)表評(píng)論 查看完整評(píng)論 | |