PMP?每日一練試題內(nèi)容(2022/11/20)
試題1
一個最近實施項目的客戶要求項目經(jīng)理調(diào)查項目交付后業(yè)務中斷和損失的問題。項目經(jīng)理向客戶解釋該請求必須轉(zhuǎn)給運營團隊,因為項目已正式驗收??蛻舨煌獠⑶疫M行了投訴。項目經(jīng)理應進行下列哪項?查看答案
試題參考答案:B
試題2
During the planning phase of a project, the project manager realized that there are differences on the understanding of the project deliverables with a project stakeholder, which results in a strained relationship with that stakeholder. What should the project manager do to address this issue?查看答案
試題參考答案:B
試題3
在回顧會上,一個敏捷團隊表示無法滿足迭代速度預測,雖然計劃了19個點,但金完成9個點。團隊認為19個點對于下一個迭代是合理的。但是敏捷管理專業(yè)人士不同意。團隊分享說部分會議是一個影響因素。敏捷管理專業(yè)人士應該怎么做?查看答案
試題參考答案:D
試題4
一名新項目經(jīng)理必須了解項目相關(guān)方在項目中的利益、關(guān)系、期望和影響項目經(jīng)理也必須利用這些關(guān)系建立聯(lián)系.下列哪一項將幫助項目經(jīng)理完成這項工作?查看答案
試題參考答案:A
試題5
高層經(jīng)理正在對一個應用系統(tǒng)集成項目進行關(guān)口審查,審查結(jié)論顯示項目的可交付成果符合驗收標準,但是仍存在一些小的錯誤,會影響產(chǎn)品的使用體驗。以下哪項是最好的建議?查看答案
試題參考答案:B
試題6
一個項目經(jīng)理想要對項目的風險進行定量分析,他有幾個專家遠在海外,但是他希望他們也能參與進來,他應該怎么做?查看答案
試題參考答案:D
試題7
A project manager runs regular virtual meetings with the tea m.During the execution phase.the project manager notices that two particular team members frequently argue and disagree,which causes meeting overruns and distractions for the rest of the team.What should the project manager do?查看答案
試題參考答案:D
試題8
一名敏捷管理專業(yè)人士注意到公司的信息發(fā)射源使用紅色、綠色和黃色交通信號燈來溝通項目進展的情況,敏捷管理專業(yè)人士應如何溝通項目狀態(tài)?查看答案
試題參考答案:C
試題9
A project manager is leading a multinational project for a customer to replace its telecommunications infrastructure with t he latest technology. The project manager learns that,in so me countries,specific environmental regulations must be followed to dispose of the replaced hardware. In the development of business arguments these rules have not be consider ed. What should the project manager do?查看答案
試題參考答案:B
試題10
Members of a project team are based in two countries. Experienced resources work together at company headquarters in country A, while the remaining resources, who deliver the project work are located in the client's offices in country B. The project manager is the client's office most of the time.Last month, the experienced resources discovered several unacceptable issues, and expressed concern that the project manager i s unable to fairly evaluate all efforts.This causes experience d resources' productivity and morale to decline. What should the project manager do?查看答案
試題參考答案:B
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權(quán)威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |