青草精品视频在线,国产白丝捆绑调教av网站,欧美一级毛片免费观看,国产999精品久久久久,a国产精品,亚洲精品午夜久久久久久久久久久,av视屏在线播放

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project consists of three major activities: A. Euro conversion development (5weeks); B. General Ledger development (6 weeks); C. CRM implementation (7weeks). Activity B cannot start until activity A is completed and an additional week is spent on resource reassignment. Activity C can only start a week after activity B has started. What is the earliest duration for the project completion?


A、12 weeks
B、13 weeks
C、14 weeks
D、18 weeks


相關試題

推薦文章
合作網(wǎng)站內(nèi)容