青草精品视频在线,国产白丝捆绑调教av网站,欧美一级毛片免费观看,国产999精品久久久久,a国产精品,亚洲精品午夜久久久久久久久久久,av视屏在线播放

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學習 培訓課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A project team reviews their monthly quality metrics. The stakeholders mandate that the new product’s production must have reject rate of <1%. What approach or process should the project manager use to meet this requirement ?
A、Statistical sampling.
B、Process analysis.
C、Plan-do-check-act.
D、Benchmarking.


相關試題

推薦文章