試卷名稱 信息系統(tǒng)項目管理師-pmp練習題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

According to the plan, 1000 hours of the work should be done with the fee of US$50 per hour by now. The project manager calculated the actual cost and realized that the team has completed the work of 1200 hours with US$40,000 according to the fee of US$50 per hour .What is the cost performance index of the project ?
A、1.5
B、1.2
C、0.833
D、0.667