試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project manager determines that the design effort is behind schedule and over budget due to scope creep. This is a result of which of the following ?
A、Excessive float.
B、Ambiguous management plan.
C、Circumvented change control process.
D、Funding restrictions.