青草精品视频在线,国产白丝捆绑调教av网站,欧美一级毛片免费观看,国产999精品久久久久,a国产精品,亚洲精品午夜久久久久久久久久久,av视屏在线播放

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(1)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(1)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Towards the end of a large infrastructure project the tension rises, and conflicts between team members occur more frequently. This affects the productivity of the team, and takes the focus away from completing the scope. To restore order the project manager putts two people off the team and replaces them with others.What strategy does the project manager use?
A、Forcing
B、Avoiding
C、Compromising
D、Exchanging


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容