試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(4)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

A project manager discovers a key feature of the deliverable deviates from the customer’s original specification, but meets quality and legal requirements With budget and schedule constraints team members suggest keeping the original design. White other team members insist on modifying the design to meet the customer’s requirement. After negotiation, the final decision is to keep the current design.The project manager should take which of the following actions next?
A、Follow the risk response matrix
B、Change the quality plan
C、Update scope management plan
D、Follow the change management procedure