試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(4)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project is completed, however, the project was delayed, causing cost overruns at the end of the project.What should the project manager do in this case?
A、Document the circumstances as lessons learned
B、Focus attrition on archiving the financial records for this project
C、Evaluate at the work of the project and compare the results to the project scope
D、Document the circumstances surrounding project completion during the validate scope process.