青草精品视频在线,国产白丝捆绑调教av网站,欧美一级毛片免费观看,国产999精品久久久久,a国产精品,亚洲精品午夜久久久久久久久久久,av视屏在线播放

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(5)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager is developing a project for a client working on a time-and-material contracts. They have performed an earned value analysis and verified that the project can be completed earlier and under the original estimated budget. The development team, however, was contracted by the project manager’s company under a fixed-price contract. This means the profit for the project manager’s company will decrease and the project manager’s bonus, based on the project margin, will also be less than expected.What should the project manager do?
A、Inform clients that they now is included some requirements that they are original deleted
B、Ask the development team slowdown in order to realize the expected profit in this project
C、Tell clients this project can be finished earlier
D、Add new works to meet the original budget


相關(guān)試題

推薦文章