青草精品视频在线,国产白丝捆绑调教av网站,欧美一级毛片免费观看,国产999精品久久久久,a国产精品,亚洲精品午夜久久久久久久久久久,av视屏在线播放

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

To meet the schedule,a decision was made to outsource part of a project to an external manufacture. What steps should a project manager follow to assess potential suppliers before awarding a contract?
A、Bidder conferences,independent estimate,and procurement negotiations
B、Quantitative analysis,bidder conferences,and critical path analysis
C、Procurement negotiations,independent estimate,and performance report
D、Procurement performance review,expert judgment and proposal evaluation technique


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容