試卷名稱 2013年上半年信息系統(tǒng)項目管理師培訓(xùn)綜合知識考前模擬題
考試中心《2013年上半年信息系統(tǒng)項目管理師培訓(xùn)綜合知識考前模擬題》在線考試
試卷年份2013年上半年
試題題型【單選題】
試題內(nèi)容

The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index (CPI=EV/AC)  value less than 1.0, it means that ( )
A. the cost savings for work completed
B. the project is ahead of its planned schedule
C. the cost overrun for work completed
D. less work was completed than was planned